Process 26 was engaged by Leighton Contractors to complete the structural design and detailing of a bulk fuel and lubrication facility.

A preliminary engineering layout had been completed by Leighton. Process 26 and a specialist engineering partner completed the detailed design prior to all detailing being completed by our in-house drafting team.

Process 26 managed the fabrication and procurement of all components and piping. The company also provided commissioning documentation and on-site assistance to ensure that all Rio Tinto’s quality objectives were achieved.